The Ouachita Citizen
Subscribe Today!
Home · News · Columns · Editorials · Letters to Editor · Sports · Tempo · Obituaries · Public Notices
Main Menu
Home
Links of Interest
Pictorial History
Polls & Surveys
Public Notices
Read Our E-Edition
Recommend Us
RSS Feeds
Search Our Site
Site Statistics
Story Archives
Top 5 Most Popular
Contact Us

Ads by Google

Current Poll
Should members of the LSU Board of Supervisors disclose who receives their scholarships?
Yes
No
Don't Care
No Opinion

View Results

Story Archives: June 2012 completion date anticipated


June 2012 completion date anticipated
by Scott Rogers - posted E-mail Story E-mail Story | Print Story Print Story 
Construction of the new Monroe Regional Airport terminal has been delayed more than a year with a new completion date set for June 20, 2012.

The original completion date for the new terminal was May 14 of this year, but the project was delayed for 13 months due to wet weather during the start of construction. The project was delayed another six months because the Federal Aviation Administration required several cables to be moved before construction began.

Lincoln Builders of Ruston continues work on the $35.5-million project. Construction began in August 2009.
.....

For the full story, subscribe to the The Ouachita Citizen's NEW E-Edition!